Hi SAP Gurus,

Ex : We have the requirement of 500 Quantity.

1. Suppose we have run the MRP RUN 1 and PR created for 500 QUANTITY.

2. After that we created the PR of 200 quantity manually.

3. Hence, the current requirement is of 300 quantity now.

4. But when we run the MRP again now it generate the PR of quantity 500.Why it is so?

It should generate the PR of 300 quantity only as the manual PR for 200 quantity exist.

What settings needs to be done? Any setting in PLANT PARAMETERS?

Please help

Navin