Should not allow TECO

Former Member
0 Kudos

Respected PP Gurus,

My client requirement is like this...

They are creating one planned order for a month and then partially converting into process order as required, also further this process order is confirmed partially, so one order they confirm twice or thrice........., now in the month end user do TECO for all the orders, in that case orders which are having status PCNF and/or PDLV also get status TECO.

Requirement is sytem should not allow TECO if any one of the above two is active.

Please Guide

Thanks in advance

Kailash T.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

Dear Kailash,

When system heaving PCNF/PDLV system allow to do TECO,there is no standard functionality to restrict,we also faced same problem,we followed created program for that and assigned user exit,now system is working fine.

Hope this may helps you

Prem.

former_member587434
Active Contributor
0 Kudos

You can map this with help of "Status profile".