on 08-03-2009 8:31 AM
Hi Experts,
We have finished good maintained with unit PC.
Now we want to scrap it or you can say we want to transfer it to another material as we sell scrap in KG.
Material to material can be tranfer when both UOM is same.
How to map this case.
Thanks ,
Amit
dear,
give alternative UOM in material master. 1 each = how much kg. try using this.
S J
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi!,
1. Create a material as scrap with material type as HALB and base unit as KG. Keep it's price control as " S" and enter it's standard price.
2. Configure a separate order type as say "SL01" (Solvation order) and assign a suitable number range to it. otherwise you can use any existing order type also. (As per your choice)
3. Now create an order for material scrap with this order type and produced scrap quantity say 15 Kg. Add the material to be scraped as BOM item and appropriate quantity. Release the order.
4. Issue the material to be scrapped against the order through MB1A (in unit PC).
5. Confirm the order through CO15 and make GR of scrap material as KG.
I think this will solve your problem. In case of any further issue please revert back.
Regards,
Uday