Former Member
0 Kudos

Hi Experts

Our client is going to change the cost center structure.

What will be the impact in MM-Purchasing other than below and how to handle?

1) Open PO's for old cost center needs to changed to new. *** We can change the cost center

2) POs with GR but no IR. What needs to be done?

Please thro some light on the above requirement.

Thanks /Karthik

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

If you have maintained the cose center in the material master you gave to chnge the cost center from their itself

Seconly for the old POs for which no GR and IIV has been made you have to change the CC

For those POs whose GR has been made need to reverse those GR and then change the PO and then once again process the GR and then IV.

I wuould suggest as in cost center we use to mainatin the valid from to valid to date so asked your FI guy to give you some time and mean time you just complete the backlog and then they will enter the validity end date in CC. By going so you dont have to reverse the IV for your old cost center

Former Member
0 Kudos

Thanks Anamica for your helpful Answer.

Let me come back if anything required further.