Hi,

As a integration part with PM module , we can integrate the WBS element in PM order. right !!!

How to integrate the PM order in PS through subnetwork ? How the order type wil be substituted. Please explain in detail. I have assigned PS02 order type and replaced order type as PM02, for example. What and how it impacts.

My purpose is to integrate PM order to PS not vice versa.

Zinni

Edited by: Makwana Zinni on Aug 3, 2009 6:08 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

customizing is found using transacton OPTP (customizing activity 'Define Parameters for Subnetworks').

When you do a double click onto the Network type subnetwork entry then you see the details.

PM orders can be used as subnetworks assigned to network activity.

The assignment of WBS elements to PM orders is done for accouting reasons.

Best regards

Peter