on 08-02-2009 8:29 AM
Hi experts,
I want to change the early start & latest start date which are in grey mode of maintenance order operation direcly instead of changing the order basic start date .How can I do it? please through some clues.thanks
Hi,
Can you please try this.
1. IW32, go to Operations tab, Select Operation 10 (assuming you only have one operation)
2. Click the "Dates" button from the buttons at teh bottom
3. On the Restrictions tab, StartPoitn, Select "Must Start On", then specify the Date you want to start the work on the right
4. Save the Work Order
Regards,
Joey
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajiba,
Please set work centre start / stop time & schduling parameter.
User this work centre in your order. Plan operations with duration .
Use Order header schduling tab for Changing the eralier start date & time.
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajib,
Early start & latest start dates (Schedule start date & schedule finish dates) are depends on scheduling type you are using. i.e. Forward, backward or capacity reuqirement.
It can not be changed manually. These dates are depends on operation hours, scheduling type and priority entered.
Sundar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.