Call Horizon % Setting in maintenance plan

shiva_08021
Explorer
0 Kudos

Hi,

I have created a maintenance plan and assigned a task list with startegy (Hour and Kilometer) and maintenance packages following below.

HMR_01 Stragedy Attached

KMR_01 Stragedy Attached

Now when I schedule the maintenance plan system should release the maintenance order (call date) exactly one week before each maintenance package.

what is the system seeting need to be done?

Kindly post your valuable suggestions.

Thanks in advance & Best Regards

Shivendra

Accepted Solutions (1)

Accepted Solutions (1)

akharisma
Explorer

Hi Pradhan.

If you want call the order exactly one week before each maintenance package, use "Interval for Call Objects = 7 Day / 1 Week" in IP30 but your call horizon must be 100%.

Regards,
Agung Kharisma

shiva_08021
Explorer
0 Kudos

Dear Agung,

"Interval for Call Objects = 7 Day / 1 Week" in IP30"

Is this interval helps in hours based stregedy?

shiva_08021
Explorer
0 Kudos

OK, thanks for your valuable answer.

Answers (2)

Answers (2)

MTerence
Active Contributor

Hi Shiv,

System will generate the call irrespective of the Strategy you are using.

If you maintain the Interval of Call Objects - 7 days say you run IP30 on 01.01.2019, system will generate call objects for the calls waiting up to 08.01.2019.

You need to make ultimate care when running IP30 with Interval of Call objects.

Regards

Terence

0 Kudos

Hi Pradhan.

Based on your requirements "Interval for Call Objects = 7 Day / 1 Week" in IP30 but your call horizon must be 100%.


Pratik Solanki