Hi All

Thank in advance for your help.

May be I am wrong but not sure, reason being new to this MRS application. My concern is when ever changing the time on planning board of assigned resource, why it not getting update to Maintenance order ?

If duration is "0" in Maintenance Order operation than by default it picking 8 hours in MRS planning board capture-1.jpg

Thanks

PM

capture-1.jpg (44.2 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Mohammed Yakub Shah
Sep 14 at 12:52 PM
0

hi,

Check this customizing.

BRuntitled.png


untitled.png (56.5 kB)
Show 1 Share
10 |10000 characters needed characters left characters exceeded

Thanks Mohammed Yakub

Thanks for taking out your precious time. I checked the same config. but its blank.

& make me double ensure that when ever we reschedule timing on planning board its will not impact on Maintenance Order operation duration. May be I am wrong but not sure.

Thanks