How to change the unit after changing costing run for packing material

0 Kudos

Hi ,

I am trying to change the unit of packing material whose price indicator is variable , but this code is included in costing run and cost is updated

hence i cant change the unit as error is coming costing is updated hence we cant change the unit.

Please solve the problem.

Regards,

Rajendra Sawant.

Accepted Solutions (1)

Accepted Solutions (1)

former_member212745
Active Contributor
0 Kudos

Hi,

You can change the UOM of that material when you will reverse each and every transaction for that material.

You have close all open PO/PR/Orders etc.

You have to delete inspection plan, tasklist. Also costing must be reversed.

All the stocks also must be removed.

Then only it is possible to change the UOM