Hi all
is there anu specifik methode for estimation of ABAP dvelopment tasks.
for example how should one etimate how long a program will take whether it is a report or a function or otheres.
Thanks.
07-31-2009 10:49 AM
I donu2019t think so if we have any Protocol for estimation. All it depends on the object which suppose to developed. Yes, to some extant you need an experience to quote an precise estimation or assessment.
07-31-2009 10:49 AM
I donu2019t think so if we have any Protocol for estimation. All it depends on the object which suppose to developed. Yes, to some extant you need an experience to quote an precise estimation or assessment.
07-31-2009 10:54 AM
No Dear,
There is no such tool. Only Experience counts.
In General, we give maximum 3 days development effort for a ordinary report program.
rest depends upon the objects requirement to be used in the code.
Regds,
Anil
07-31-2009 11:13 AM
Its all depends on the task and type of requirement u have.
There is no tool to estimate the duration of task.Only from experience ur going to know that.
Regards,
Lakshman.