PR Release Procedure..

Former Member
0 Kudos

Hi,

My client has only one level of Release PR.. I activated overall release also.. During collective release in ME55 ,there are two incicators one is for item release and other one is for overall relase.Eventhough we activated overall release they need itemwise release also.. when i do testing itemwise is not working it shows only overall relase.. pls tell me any settings for both iemwise and overall...

regards

SAP MM User

Accepted Solutions (1)

Accepted Solutions (1)

mohd_uzairhussain
Contributor
0 Kudos

Hi,

As per SAP standard u can have either Header Release or Item level release but not both at the same time.

Regards,

Uzair

Answers (2)

Answers (2)

former_member329706
Active Contributor
0 Kudos

Hi,

You can have only one release procedure that either item wise or overall release in std sap.

regards,

patil

Former Member
0 Kudos

Hi,

There is no settings to have PR release both iemwise and overall...