Operation selection of task list when attaching to an order

Former Member
0 Kudos

Hi all,

When I am attaching a General Task list to an order (Extras-->Task list selection), the system does not ask me to select the operations from the task list in QAS. It is copying all the operations from the Task list to the order.

My requirement is that I need to select only few operations from my Task list when I am attaching the Task list.

But it is asking to select the operations from the Task list in our DEV system. Can anybody guide me make the settings in my QAS?

Thanks in Advance,

Babu.K

Accepted Solutions (1)

Accepted Solutions (1)

seran_k
Active Participant
0 Kudos

Please check in SPRO under node 'Default values for tasklists and profile assgnments' whther you have selected for operation selection and operation sorting for the related order type. If not 'select' them.

-Seran

Former Member
0 Kudos

Hi Seran,

Thanks for the valuable input.

Still it is not working in our QAS. In fact, I am not maintaining this settings in the DEV client but it works.

Can you please help me to resolve this issue?

Thanks

Babu

Edited by: BabuCS on Jul 31, 2009 11:14 AM

Former Member
0 Kudos

Solution is

- Go to IW32

- Menu path: Extras->Settings->Default values

- Go to the Control tab

- Set checkboxes for "Operation select" and "Work cntr selection"

- Save

- Exit order

- Re-enter order

- Try adding a new task list

Answers (0)