on 07-30-2009 12:24 PM
Hi Expurts
where is the integration betwwen Asset and Project Systems please explain with examples.
Regards
Ragini
Define Investment Profile (search the IMG tree for Projects as Investment Measures), Investment Profile will be assigned in the WBS master data to generate AuC for WBS, the final project settlement settles costs from AuC to the Final Asset(s).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Assets and PS will be integrated with the WBS elements,
All the Project systems are created in to WIP and moved to WBS element which is linked to cost code and settled to Final Assets.
Project will be created as WBS elements and PS is also used for opex POs.
Regards,
Padma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.