Dear all

Here is the problem what I had facing .

1 I had planned/attached the material to activity in cj20n.

Say material cement------100bags

the system generates Reservation no. , Purchase Req. no, with Procurement type

Requisition + Reservation for WBS element for the same.

2 Now when we released the material PR through Released strategy

The reservation no. disappears & the procurement type gets change to

Third party WBS element.

Due to which we cannot make PO for the said materials.

Question:-

I donu2019t want the system to change to Procurement type of material.

It should remain the same as at the time of planning.

I.e. Requisition + Reservation for WBS element, with the reservation no .

3 The system allows to change the qnty of material, which has planned in cj20n & which has been released converted in PO.

Say material cement ---100bags

System allows the change the qnty >100 & < 100 bags

Question:-

The system should not allow to change the quantity of material which has been released & converted in PO.

the system should show error.

Thanks to all in advance