spliting of planned order to process order

Former Member
0 Kudos

Hai gurus,

I have an issue:

For example if i have requirement for 1000numbers of finished goods, and if I run MRP and create a planned order under

PI scenario, But I want to create process order for the qty daily (For example 100 numbers), can I do this, and also this

daily qty may vary based on the available resources,( some times it may be 100 or 110 or 120) for that day production.

If that is the case can I create the process order daily based on the master planned order .

waiting for the positive reply.

with regards,

sekar chand

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Through COR7 - Individual Conversion or COR8 you can partial convert your planned order to the process order as per your resource availability you can define the order quantity during conversion.

Regards,

R.Brahmankar

Former Member
0 Kudos

hai Brahmankar,

Thanks for your reply my problem is solved

regards,

sekar chan

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can do partial conversions of your planned order into process orders.

MRP will look at both your planned order and your process orders and issues messages accordingly.

Hope it helps.~p.