Hi Friends,

I have a requirement where in user should not be allowed to change the profit centre of Project Definition and WBS via tcode CJ20N and change the profit centre of Project Definition, WBS, Netowok and Activity via tcode CNMASS.

I could achieve the profit centre lock for PD, WBS and Network by Implementing BADIs PROJECTDEF_UPDATE, WORKBREAKDOWN_UPDATE and WORKORDER_UPDATE.. The implemented BADI 'WORKORDER_UPDATE 'is reachable while changing profit centre of Activiy as well. But the details of the changes of activity is not visibile inside BADI.

If anybody has any input for this, it would be appreciated.

Thanks,