Hi Experts,

Some one can help my question is how to configure Shipping automation my user want to load automatically

Scenario: When driver comes to Dispatch coordinator he will provide all the details, Dispatch coordinator will take the 1st weight

of the truck then driver will go into the store to collect the stock he will load the truc then back to the weighbridge for 2nd

weight that time the weighbrdige operator entering all the details so useer want to get the information automatically when the

Delivery No enter into he Weigh bridge system automatically all the information should be there no need to enter again by

Weighbridge operator in this way he want to save the time.

Thanks,

MH

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jul 29, 2009 at 10:12 AM

    Hi

    we are using the similar concept through Z-Process of First Weight and Second weight.

    You must be generating some transaction no. ( No. Range ) when the first weight saved, and that should me maintained in a Z-table. Either take the detail from that Z-Table or in Z-table you also save the Delivery No. (before doing the PGI) with reference to that the user will do the first weight, and so you may get the detail of Delivery also.

    Hope you undearstand and able to map the scenario.

    Regards

    Amitesh

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Amitesh Anand

      Hi Amitesh,

      May I know which User exit you are using for this scenario, for first weight as well as PGI

      Thanks in advance