Hello,

I have the following scenario:

Make-to-order sales order items with a requirements class which triggers automatic MRP. The planned orders are generated by the MRP with Scheduling defaulted to '1' (Determination of Basic Dates for Planned Orders).

We need to have it running with Scheduling '2' (Lead time scheduling) instead, like in the screen copy. Is there a way out of SD to influence it or is it in PP config and where?

Thanks for any hint.

Attachments