on 07-27-2009 5:04 PM
Hi, can anyone advise how we can use the planned hours instead of actual hours to generate the billing request for RRB? Currently am using source '0001' 'Actual Cost - Line items'. I did not find another suitable source which can be used. Any userexits?
Thanks
PP
You need to select the source 0021-Planned costs.
Thanks