BAPI_PRODORD_CHANGE is not updating Schedule Start and End Dates

mantrishekar
Active Participant
0 Kudos

Hi All,

In Transaction CO02 am trying to change Schedule Start Date and End Date and am able to do it succeessfully through Transaction.

I want to Perform same Operation using BAPI_PRODORD_CHANGE but it is not updating.

Could anybody faced this issue earlier.Please help me to resolve this issue.



Regards,

Shekar.

Accepted Solutions (0)

Answers (2)

Answers (2)

Caetano
Product and Topic Expert
Product and Topic Expert

Hello

In your production order type scheduling parameters (OPU3) you should define if the scheduling will be based in production dates, so that it is possible to input the scheduled start and finish date in transaction CO01. I assume that the same thing happens with the BAPI and you will only be able to input the scheduled start date if this flag is checked in customizing.

Regards,
Caetano

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

You should also check the following note:

1956185 - Create order using BAPI: Scheduling of production dates

Regards,

Caetano

janbuchmann
Contributor

Thank you so much for pointing out this SAP note! This solves a long-pending issue *ThumbsUp*

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

You are welcome!

former_member185450
Active Contributor
0 Kudos

Hello Mantri,

Hope you are executing the BAPI_PRODORD_CHANGE with BAPI_TRANSACTION_COMMIT

as per my knowledge and understanding system should update..

Kindly check and update

Regards,

Venkatesh Babu..