Plan driven Procurement - PR transfer from ERP to SRM as SC

Hello.

I'm using ERP 6.0 EHP4 and SRM 7.0 and i'm implementing the Plan Driven Procurement Scenario.

I believe I've made the necessary customizing, however I cant seem to transfer ERP purchase requisitions to SRM as Shopping carts.

When I run the bbp_extreq_transfer report, in the SMQ1 transction I get the ANORETRY status.

Has anyone had this problem?

Tks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Jul 24, 2009 at 12:31 PM

    Hi,

    In addition to the required settings for PDP process, please verify

    1. Whether you have created logical system entry (SALE txn in ECC system) with respect to the logical system defined in the "T160PR" table and

    2. You have maintained RFC connection for the same in SM59 and ensure password of RFC user is correct.

    Regards,

    GM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 24, 2009 at 02:57 PM

    Hello CLOURENCO

    Guess you have gone through the below note,if not..plz will help

    Note 1027506 - BBP_EXTREQ_TRANSFER: ANORETRY for PR with different vendors

    Arshad

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 24, 2009 at 04:46 PM

    Hello,

    With ECC6.0 EhP4 & SRM 7.0, we no longer need bbp_extreq_transfer report.

    The transfer happens via PI. You have to activate event linkages for BUS2105 Changed, create, sourcing requested (WS 53800009) & implement the BADI ME_REQ_SOURCING_CUST.

    Hope this solves.

    Thanks

    Ashutosh

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Mangesh,

      Please check SLG1 in SRM . Also check if your RFC user against the ECC entry channel(in Org structure) has got corrupted.

      Thanks

      Saji George