SUBC (Sub Contracting) PO Reservation.

former_member467138
Active Contributor
0 Kudos

Dear All,

I am facing problem in SUBC(Sub contracting) PO Reservation.

My problem is how to delete SUBC PO reservation always it is showing SubReq in MD04 and every plant level MRP its create PR for that reservation.

Thanks&Regards.

Arun Pattar

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

HI Arun

I am also having same problem.

I have subcontracting PO, In MD04 for component material, Some sub req has generated.

Now I need to delete that unnecessary sub req which is for component material.

Action Taken....Deleted Pur req, deleted subcontracting Po and also ticked on completed delivery ind.

But still prob has not resolved...still in MD04 Sub req are showing

Can you provide me solution fot this issue.

Thanx...

Trupti Bhujbal

former_member467138
Active Contributor
0 Kudos

self resolved using sap standard programme

rm06c020

Former Member
0 Kudos

Hi

Yes you need to close the PO. With out which the reservation is not cleared

krishna

former_member467138
Active Contributor
0 Kudos

Yes Krishna,

I have aleready closed po eventhogh reservation are still exist.

Former Member
0 Kudos

Hi

I need some more details like GR processing time, inhouse production time , MRP interval etc to analyse the issue. the issue is related times only. otherwise i dont see any problem.

Krishna

former_member467138
Active Contributor
0 Kudos

Hi ,

Gr processing time is 2,in house production time 30days but I donu2019t know what does MRP interval mean?

Arun

csaba_szommer
Active Contributor
0 Kudos

You recognised that the subcontracting reservation comes from the PO, so you have to close the PO to get rid of the reservation. Until you have an open subcontracting PO with component list, SAP will generate reservations for the compoenents.

This works similarly to PrdOrds...

If you are speaking about subcontracting reservations that exists even though the PO is closed, please check OSS note 115899, 128061.

Please also check OSS note 550219 about subcontracting in MRP.

Regards,

Csaba

Former Member
0 Kudos

Hi

The subcontarcting is coming from the routing opertion ?

If yes then do the TECO for the production order, which is used this subcontarcting PO.

Thanks

S.Murali

former_member467138
Active Contributor
0 Kudos

Hi Murali,

Subcontracting comes from routing but u doesnu2019t have production order for that.

Arun