on 07-23-2009 10:28 AM
Hi Team
Pls suggest me steps into Notification processing. I am not clear with Rel, Teco status. When to release & tech. complete this.
Thanks
When any notification is created u2018Outstandingu2019 status (OSNO) is attached to it.
Then defects are recorded if any, task and activities are assigned to it.
Tasks are also having status, when it is created they are in outstanding status,
At the same time notification is put 'In process' (NOPR) by releasing it. Then task are put 'In process' (TSRL) status. In process means work is going on that task.
After completion of task, the status has to be changed to 'Completed' (TSCO)and 'Successfully Completed' (TSCO TSSC).
Then only notification can be closed (NOCO NOTE ATCO).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.