Requirement Grouping

Dear Experts,

Want to know about the concept of "Requirement Grouping " and in which scenarios it will be applicable.

Very much Appreciate your guidance,

Dileepa.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jul 23, 2009 at 05:06 AM

    Hi

    This concept normally used in PP(Production planning).

    It means group the similar requirements in one planned order, instead of creating more number of planned orders.

    Basically this requirement is grouped using the lot sizes in MRP.

    For requirement grouping you can use the following Lot sizes

    FX -- Fixed order quantity

    If you use this you can fix the qunatity for planned order creation.

    EX: Your lot size is FX =100

    Requirement is 25,35 and 40

    So the system will group requirement and it will give you the planned order for 100

    Lot Size MB --- Monthly lot size

    Using this you can group the monthly requirement into one lot

    Lot Size WB ---Weekly lot size

    Using this you can group the weekly requirement in one lot

    Thanks

    S.Murali