on 07-23-2009 5:19 AM
Hi All,
In our business we have 12 operation stages in routing and total process passes through 4 depts.We have 4 SAP Logon id for these dept.We are using 4 Milestone Confirmation stages (Control Key PP03) and separate dept. confirm their stages by using CO11N T.Code.Now I want o check authorization on the basis of Order Operation Activity number wise or Work Centerwise so that no other dept can confirm other stages only responsible dept. has authorization to confirm their stages.
Please let me know how can I incorporate this things so that it works.I have checked authorization objects for Confirmation but it is not there.Please guide me.
Thanks & Regards
Nirmal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Try with this User Exit's
CONFPP01 PP order conf.: Determine customer specific default values
CONFPP02 PP order conf.: Customer specific input checks 1
CONFPP03 PP order conf.: Cust. specific check after op. selection
CONFPP04 PP order conf.: Customer specific input checks 2
CONFPP05 PP order conf.: Customer specific enhancements when saving
CONFPP06 PP Order Confirmations: Actual Data Transfer
CONFPP07 Single Screen Entry: Inclusion of User-Defined Subscreens
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.