Hello All,

I am looking out for a Solution to create PO from Contract in SAP SRM 7.0.

We have Extended Classic Scenario in place.(PS- We cannot switch back to Classic scenario ).

When we create PO from Contract, it removes Outline and Only Flat Service Line are seen in POs.

We contacted SAP for the same and SAP said this is how SAP SRM works for PO in extended Classic scenario. We are looking out for a solution where we can have Outline on PO line item if PO is created from Contract.

Note - If I create PO from RFx response then PO is created with Outline as Expected.I am removing GROUPING_LEVEL as blank.

Is there any parameter which we can set to enable Outline for Service POs.

We tried setting few parameters like ITM_TYPE as 'HIER' ; SUBTYPE as 'EP' , but its didn't help.

Any pointers to this problem is highly appreciated.

Thanks in Advance!!!

Regards,

Vikas

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Sep 07, 2018 at 01:49 AM

    Dear Customer,

    Unfortunately in when manually create SRM PO (without PPS active ), it is not possible to create hierarchy.

    However when PR as service outline hierarchy, transferred to SRM Shopping cart ,after assigning contract, and then convert to SRM PO.

    This service outline hierarchy can be adopted in to SRM PO.

    You could also add contract in PO item , if the draft PO was created from above PR directly I think.

    Please understand directly add hierarchy in BBP_DOC_CHANGE_BADI maybe trigger error in in transfer stage.

    Best regards

    Summer Wang

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 07, 2018 at 01:50 AM

    Dear Customer,

    Unfortunately, when manually create SRM PO (without PPS active ), it is not possible to create hierarchy.

    However if PR had service outline hierarchy, transferred to SRM Shopping cart ,after assigning contract, and then converted to SRM PO.

    This service outline hierarchy could be adopted in to SRM PO.

    You could also add contract in PO item , if the draft PO was created from above PR directly I think.

    Please understand directly add hierarchy in BBP_DOC_CHANGE_BADI maybe trigger error in transfer stage.

    Best regards

    Summer Wang

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 23, 2018 at 11:07 PM

    Hello Summer Wang

    As PPS 2.0 is active in our landscape,we understand by tweaking the PS item types and Configurable item numbering, the hierarchy creation in SRM PO is possible and also the replication of the PO line items in a similar representation to the ECC

    Could you please help by providing any pointers?

    Thanks

    Nag

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.