Quick question:

In which part in customizing can I select plants to do availability check? I have 3 plants at the moment but the customer wants the system to only check in 2 of them?

I know I can set the material master using checking groups and checking rules but in this case I would like to select only one plant

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Ability check will happen on base on delivery plant level which come from first preference give to customer info record pant then customer master plant and last material plant if plant not find in this 3 u can enter plant manual so while doing atp check it will consider any plant weir system find proper record although u have 10 plants no maters

Ahmed

Answers (2)

Answers (2)

former_member1249468
Contributor
0 Kudos

Hi Maria,

We can select the availability check at sales order line item level,if the plant is not relevant for availability check .Do not check the "Check item availablity" at line item level.System generally checks the availability at delivering plant level.

Regards,

Pasapula.

Former Member
0 Kudos

Hi

Check the settings in SPRO-SD- Basic Functions-Availability Check and Transfer Of Requirements-Availability Check

Regards

Chandra