BOM exploded to network (CN33) but no component scrap is taken into account

104 Views

Dear Experts,

We have a BOM with 100 components transfered into a project network with transaction CN33.

In the BOM, on item level, we have stated component scrap %.

MRP takes these component scrap % into account.

However, if we confirm a project with transaction CN25 the proposed/booked goods movement 281 does not take the scrap % into account.

Example material BOM A (base quantity 100) contains component B (quantity 100 and component scrap 10%). MRP calculates with requirement 100 for material BOM A a requirement of 110 for component B. However, if we explode material BOM A to a project with transaction CN33 and we book the confirmation with transaction CN25 the the proposed/booked goods movement 281for component B is 100 (and not the desired 110).

We would like to take the component scrap % into account at goods issue of the project.

Is there a setting in customizng or the material masterfor this (or is the only option to use two BOM types for this)?

regards, Herman Alkemade