Requirement Grouping

Mat requirement grouping is not happening at Level 1 WBS.

Following setting are maintained

1.Autmomatic Req Grp is set at Proj Def

2. Level 1 WBS is made as grp WBS

3. Periodic lot size is maintained for the Mat as MB

What else is missing?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jul 23, 2009 at 05:56 AM

    Hi

    Have you using the MRP groups ?

    if yes

    Go to SPRO----Material - Procurement --Activate MRP group for Requirements grouping

    Enter the Plant and MRP group and check the Grouping check box.

    Thanks

    S.Murali