hi everyone,

can anyone plz tell me the answer for following

. In which areas of the system can you specify whether and how MRP is to be carried out at a plant?

A. Material Master.

B. In the customizing IMG activity for Material Requirements Planning

C. In the customizing IMG activity to activate MRP and setting up the planning file.

D. MRP1 view of the Material Master.

E. Only a) and b) above.

thanks in advance

shreek

Accepted Solutions (1)

Accepted Solutions (1)

former_member184655
Active Contributor
0 Kudos

Dear Shreek,

For running MRP,

1.You need a proper material master and proper BOM and rtouting for the procurment type E materials.

2.Proper MRP type and MRP datas in MRP1,2,3,4 views along with the settings in OPPQ - carryout overall parameters for MRP at

plant level,activating MRP for plant and planning File Entries.

3.Without any planning file entry you cannot run MRP.

4.MRP steps includes

1. Checking Planning File entries

2. Net Requirement Calculation

3. Calculating Procurement Quantity

4. Scheduling

5. Determining the Procurement proposals

6. BOM explosion & determining Depenedent Requirements

7. Creation of Exception Messages

Also check this link to explore more on MRP,

Regards

Mangalraj.S

Answers (7)

Answers (7)

former_member219179
Contributor
0 Kudos

Hi Shreek,

100% am confident the option is E

Cheers,

Kumar.S

Former Member
0 Kudos

Thanks All for your responses.

As most of you have agreed 'E' is the right option, Is that mean option C completely ruled out.

So,

Can we run MRP without setting up planning file ?

plz give your opinions,

Thanks in advance

Shreek

former_member219179
Contributor
0 Kudos

Hi Shreek,

As one of our expert Mangalraj say in his reply Without any planning file entry you cannot run MRP.

its absolutely correct.

Cheers,Kumar.S

Former Member
0 Kudos

Hi Kumar,

Thanks for your reply,

So the answer for the question is

A, B, C

is that right?

thanks in advance

Shreek

Former Member
0 Kudos

Hi,

The option is 'E'

Regards,

Andra

Former Member
0 Kudos

Hi

Below are the prrequisites to run the MRP for the particular plant form MM perspective.

1) Plant must be activated for MRP in customizing under MM>CBP>Planning>Activate

2) Plant parameters must be maintained in Customizing under MM>CBP>Plant parameters

3) Material master have to maintained for atleast MRP1 & 2 views

4) MRP type ND-Noplanning must not be used in the material master MRP view

Hope you can decide the answer now.

Thanks / Karthik

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

The MRP type in MRP1 view of the Material Master is play vital role for Material Requirements Planning .

But the settings are made in each material master in the MRP 1,2,3,4, views which decide MRP.

For example:

MRP Type defines how a material is planned

MRP Types are defined at Plant level

Minimum stock levels can be managed using Safety Stock

Template recommends limiting MRP Types to PD, V1/VB and ND.However PD is highly recommended on the principle that planning is based on actual requirements and not just a fixed reorder point.

Regards,

Biju K

Former Member
0 Kudos

Hi,

The option is E.

Thanks

Shashi

Former Member
0 Kudos

Its E

Former Member
0 Kudos

hi,

The factors which influence the MRP is

1) In Material master u need to maintain the MRP views and there in MRP1 view.MRPtype,and Lot Size need to bemaintained

MRP2 view:Procurement type,Scedule margin keyinhouseprod time,gr Processsing time,Planned delivery,

MRP3 View:Strategy gtoup,Availabilty check...

2)in OPPQ for u r plant MRP settings are to be done

3)activate the palnning file entry

Hope this helps u

Regrds

Sravanthi