Hi anybody,

In VC BOM scene, when i va01 create so, system give me a error message: "

External procurement not defined for material ZCCF_CPU

", can u tell me how to do it ? many thanks ~

  • Configuration profile:

  • Material Master Data:

material ZCCF_CPU_300,the component of ZCCF_CPU

(ZCCF_CPU_400 and ZCCF_CPU_500 is the same as the ZCCF_CPU_300)

  • BOM

ZCCF_PC

ZCCF_CPU

Accepted Solutions (1)

Accepted Solutions (1)

solved it, i give a wrong schedule line category .

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

In MRP-2 view of material master, there is one field for Procurement Type. Check whether you have maintained any value here.

0 Kudos

Thanks, But in the procurement type i have maintained 'E' all the above materials, my test materials are finished or semifinished product.