Hello SAP Experts ,

I'd like to ask about the commitment when releasing project purchase requisitions with Item category N (Non Stock Items) the system trigger commitment on the requested project But when using item category L (Stock Items) system did not release commitment , could any one let me know why that behavior and if i can change this behavior to trigger commitment in all the cases.

Thanks a lot for your time.

M.Ezz

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Paulo Vitoriano Nov 16, 2016 at 03:14 PM
0

Hi Mohamed,

If you are using valuated project stock, please confirm that respective BS materials account is defined as a Cost Element. Everything that is posted in CO must be a cost element.

Regards,

Paulo

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Hi Paulo ,

Thanks a lot for your answer but let me confirm with you that the planning and actual material movement from stock to project id done through consumption account and the consumption account is already defined as cost element why i should define the balance sheet account as cost element ?

Thanks.

M.Ezz

0

Hi Mohamed

That is only in case you are using valuated project stock. Otherwise you will not see it in the PS InfoSystem, neither as stock nor as commitment.