PS - CO || Commitment with PRs Item Category L (Stockable)

Hello SAP Experts ,

I'd like to ask about the commitment when releasing project purchase requisitions with Item category N (Non Stock Items) the system trigger commitment on the requested project But when using item category L (Stock Items) system did not release commitment , could any one let me know why that behavior and if i can change this behavior to trigger commitment in all the cases.

Thanks a lot for your time.

M.Ezz

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 16, 2016 at 03:14 PM

    Hi Mohamed,

    If you are using valuated project stock, please confirm that respective BS materials account is defined as a Cost Element. Everything that is posted in CO must be a cost element.

    Regards,

    Paulo