Hello,
I have a process order with total qty 20000, delivered qty 18000. FINAL confirmation is done, the order now has status MSPT, CNF, DLV, PRC, GMPS.
When I run KKAX for this order, as it has DLV so the expected result shoule be NO WIP, but it still have WIP. can anyone let me know what's wrong with this order or what i need to check in our systerm?
Many thanks
Mavis
Hi,
The process order will calculate WIP till it reachs delivey completed or tech Completed status. Based on the details still there is diff of 2000 Qty on order so it will calculate WIP. Its standard SAP. If you want to calculate Variance you need to change the status to tech completed and then calculate variance
This may help
Regards
Shantanu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.