on 07-20-2009 2:03 PM
Hi SAP Gurus,
I want to know @ what conditon
1.Required capacity will be available for Workcentres
2.If required capacity is not not there what will be the impact?
3.Also throw some lights on Available capacity and Remaing capacity.
Awaiting for your positive reply.
Cheers,
Kumar.S
Hi
1.Required capacity will be available for Workcentres
You need to maintain the standard available capacity in workcenter, the std available capacity is called as required capacity of the workcenter.
Example:
Start 07:00:00
Finish 18:00:00 Capacity utilization 100
Length of breaks 00:00:00 No. of indiv. cap. 1
Operating time 11.00 ; Capacity 11.00 ; HR
2.If required capacity is not there what will be the impact?
If you are not maintained this you are not able to do the capacity planning for your orders.
.Also throw some lights on Available capacity and Remaing capacity.
The available capacity is total available capacity of your workcenter
The remaining capacity = Requirements- AvailCap
Example:
Requirements AvailCap. RemAvailCap
50 Hours 100 Hours 50Hours
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar and Murali,
I have simulated but in my case Required capacity gets calculated even If i choose capacity category as Machine or labour based on Processing formula what i have mentioned in workcentre under Capactiy tab and compare with the standard values what i have mentioned in routing + Setup time.
Also i can able to see this in Planned Order right.
Requested you to correct me if am wrong.
Mr.Murali i cant able to understand what u have mentined for remaining capacity,you mean to sayRemani cap = Reqmts - Avail cap ok but exmple what you have given needed little more clarification.
This part am not clear.
Example:
Requirements AvailCap. RemAvailCap
50 Hours 100 Hours 50Hours
Cheers,
Kumar.S
Dear Kumar,
example
u have a order which required to process 10 hrs (availble cpacity & required capacity)
u have completed the work in 9 hrs
so here remaining capcity is 1 hr
when u confirm the order system will ( free the capcities) will set to zero for this work center
and u can start next order
Regards
kumar
Hi
Take exmaple
your total avialble capacity in your workcenter is 100 hrs / week
in that you have requirement (Production orders) is 50hrs/Week
The remaining available capacity in your work center is = 100-50 = 50hrs/Week
So still you can use this work center for cpapcity planning, because your remaining available capapcity is 50 hrs
I hope u understan the example
Thanks
S.Murali
Dear Kumar,
Required capacity will be available for Workcentres
the capacities u give in work center i.e start time, end time will taken as availble capacities for production process.
If required capacity is not not there what will be the impact
if there are not enough capacities availble, then system gives Mssg as capacities are not availble, while creating production order.
Also throw some lights on Available capacity and Remaing capacity.
when u confirm the order, the capacities for that order will set to Zero i.e availble cpacities & remaining capacities.
Regards
kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.