How to set the error message when LIV amount over PO amount ?

Dear experts :

I create a PO without GR base IV , and I have setting limit in OMR6.

I hope system show error message when the LIV amount over PO amount .

But in fact , when LIV amount over PO amount , the system didn't show any message.

Hope someone can tell me ,besides OMR6, what setting I need do?

Thanks a lot.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jul 20, 2009 at 09:45 AM

    Please use T code OMR6 & assign tolerance key for plant & Tlky -> BD TO "zero".

    Regards

    Bhavesh Mistry

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.