PO item partial GR caused commitment issue

hi,

we have a probem caused by the PO item partially GR. I would like to distingish the GR for a PO item whether is a partially or fully. We have a customize report for generating the commitment and send to other sysem.

the problem here Say,

one po Item with 1000 , then do partially GR witth 100, so the commitment about should be 900. But currently the logic doesn't works. It considers that the commitment amout is 0. Appreciate your voices, any good way to pick the 900 up.

thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jul 20, 2009 at 06:48 AM

    HI..

    PO item wise value can be picked from EKPO,where as the partial GR for that particular PO (EBELN) and for that item(EBELP)can be derived from EKBE table where the movement type is '101' or purchase history category'E' then pick the value EKBE-WRBTR(doc.currency) and for PO item value try to get the value from net value or gross value it all depends on the requirement.

    Commited = EKPO-Gross/net value( for that item,EBELP) - EKBE-WRBTR.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.