on 07-18-2009 2:02 PM
where we cal assign cost center in Pcc? work center not used in routing .
Dear Saroji,
what is your exact query?
Product cost collector is used a cost collecting object in REM scenario.
In REM scenario rate routing will be created for all the material's for which backflush is to be done for posting their activities in MFBF.
Cost center will be assigned to the work center in the costing tab.
Come back with your further queries.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Producr Cost Collector uses the rate routing. In rate routing we should maintain the work center. In work center cost center is maintained. Without work center it is not possible.
So you need to maintain routing or rate routing.
Regards,
V. Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.