07-18-2009 9:32 AM
Hello,Friends,
Iam PP consultant and facing a problem of BOM components uploading through BAPI,for creating of the Network (CN21)
we have 300 components in the network activity and while uploading the BOM through BAPI , only 295 components has been uploaded.Others components has not uploaded.
Please suggest me what will be the Problem? and
What is the solution for the same?
Regards,
MYS
07-18-2009 9:47 AM
Hi,
Check that five records where are correct or not. and reupload with only five records.
Thanks,
07-18-2009 9:55 AM
in customizing availability checked has been applied ,for this reason one additional screen is appearing in BAPI for all these components
How this screen could be by passed
07-30-2009 12:54 PM