Display the PO in the capacity leveling

Former Member
0 Kudos

Hi,

in the capacity leveling CM21 there is a table section.

In the table section I get Production order and planned order.

I just want to display the production order in this sections or in the oders pools.

How can I customize the system.

Thanks

Dede

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Use CM25 and the selection profile you can select order.

Thanks

S.Murali