How to assign order type NB for procurement type X for Planned Order

Former Member
0 Kudos

Hi,

This is the scenario what we needed. System should take order type NB for procurement type X while generation planned order.

We are not converting planned order to PR.

I tried assigning though MRP Group but is is not taking. we are simulation the MRP for Vendor .

Thanks and Regards

Ragahvendra Pai

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Ragahvendra,

NB is a purchase req. MRP doesn't like to assign those to X procurement.

However, you can immediately after MRP runs CONVERT all X procurement planned orders to purchase reqs. Use program RMCVPLRQ in batch. Make sure you select "X" for procurement type.

Manually you can run MD15 against a single matl/plant combo to get the same effect..

Rgds,

DB49