Dear Fnds,

Iam Using Billing plan in Order....1st 80% and second 20%.....and Order qty is 10.when iam maintaining the Milestone in Order in billing type field i have maintained F2.

But here i need to do the 1st invoice w.r.to Delivery.

But system is not allowing me to do billing w r to Delivery.

Thanks in Advance

Regards

raj.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

What is the error message you are getting? Did you check the Copy contol setting between the respective item category in VTFL?

Thanks,

Raja

Former Member
0 Kudos

Dear fnd,

iam getting in Error log:0080000192 000000 The document is not relevant for billing

My doubt is ...can we take Ref Delivery doc to create Milestone.

In Item category Billing Relevance field:I

and Billing Plan Type:01

How can i take Delivery doc as ref....

Thanks in Advance

regards

raj.

Former Member
0 Kudos

Hi,

As per general this should be Order related, but i think you can do by reference to delivery, (not sure though)

Please check whether the delivery is picked completely or not or is blocked or item rejection.

Thanks,

Raja

Former Member
0 Kudos

Dear all,

I had maintained MIlestone in Order ...as 80% and 20 %.

this 80% i need to bill teh customer after dispatch of materials...so here i need to take Delivery as Reference..

When iam trying to take Delivery document system is not allowing adn not copying 80% of the Invoice.

How can i do it for this Requirment .

Thanks in Advance

Regards

raj.

Answers (1)

Answers (1)

former_member184555
Active Contributor
0 Kudos

Hi

Make a check in the billing program...to check the delivery while creating the billing. This should be more appropriate than creating billing referring the delivery.

Thanks,

Ravi