on 07-16-2009 10:01 AM
Good morning,
I am planning a product in a sim version in APO, if I do a regen planning run it works but if I run the same scenario (and reset the results) with a net change it is not included (not planned) in the planning run.
Am I missing something obvious??
Thanks in advance.
Hi UKuser,
1) It may happen that the product view and background job will have two different
heuristics selected, please check
2) Check the job log and application logs during the time of job run.
3) In background job, if you select entire planning horizon, then it will plan. In
product view, it works based on SNP horizon
4) Before u retry, delete the existing planned orders and retry
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the input,
If i run the heuristic in the product view (/sapapo/rrp3) APO will generate the required planned orders but if I leave it to the background planning run it does nothing.
I have checked ECC to make sure the materials are in the planning file.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prasad,
Planning run can be performed both with netchange as well as with
regenerative mode.
Every time, when planning relevant changes are done in system, system
automatically sets up planning file entry for the location product
combination.
If you select net change method, only those items with plannning file
entries will be planned in planning run.
If you select regen mode, the entire sequence will be replanned
irrespective of planning file entries.
Again, the selection of net change or regen mode is purely depends
upon the client/business depending upon the requirement.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
1. Check the Planning File entry SNP if the indicator is set (/sapapo/rrp_netch).
2. Are you executing SNP Heuristic at MRP Area Level?
Thanks,
Sendil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi UKuser,
In netchange mode, it will give planning results only if you carry out planning relevant changes
for the specified location product combination. The change should have been carried out
after the previous planning run. If there is no change carried out for the combination after the
previous run and if you execute net change run again, it will not give any results. This is
standard functionality. Only in regen mode, the location product will be entirely planned
again.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I did not get you properly. Please check You have set the indicator to be able to run net change planning within the SNP heuristic. To check this Go to /sapapo/mvm.
The indicator is only taken into account for the active planning version.
Thanks,
Satyajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.