Former Member
Jul 16, 2009 at 04:23 AM

Planed order type NB instead of LA during MRP Run

483 Views

Hi,

All my components are externally procured and I maintained planned delivery time for scheduling purpose. But system is automatically picking the order type LA which is inhouse production when I am running MRP. What setting I need to make for MRP to select order type NB for Planned order so that system picks the plnned delivery time form material master to calculate basic finish date.

We are generating planned order instead of Purchase requistion through MD02 setting.

Regards

Raghavendra