Skip to Content
author's profile photo Former Member
Former Member

Planed order type NB instead of LA during MRP Run

Hi,

All my components are externally procured and I maintained planned delivery time for scheduling purpose. But system is automatically picking the order type LA which is inhouse production when I am running MRP. What setting I need to make for MRP to select order type NB for Planned order so that system picks the plnned delivery time form material master to calculate basic finish date.

We are generating planned order instead of Purchase requistion through MD02 setting.

Regards

Raghavendra

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jul 16, 2009 at 05:18 AM

    Hi!,

    If your procurement type is "F" (External Procurement) then system will create a planned order of NB type only irrespaective of what MRP parameter you select, but if you are using proc type "X" then MRP will create a LA type of planned order only.

    Regards,

    Uday

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      I tested the above scenario for my BOM.There are totally 5 levels and for all materials I made procurement type F.

      I did the setting as mentioned above for Md02.

      Only first level materials are exploding.

      i thing what system is doing is right.You can have one Raw material under another.you need to make procurement type X for that.

      @Eshwer can you test scenario with more than one level.

      Thanks and Regards

      Ragahvendra Pai

  • Posted on Jul 16, 2009 at 04:47 AM

    HI,

    Idealy if the procurement type is F , there should not be any Inhouse production time in material master as its not relevant, and there should be maintained planned delivery time.

    But you can try If you are looking at PR creation, yes need to assign the PR Document type NB to a MRP group in transaction OPPR. Assign this MRP group to the material master.

    Check and revert back.

    Hope it helps you.

    Regards

    Ritesh

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 21, 2009 at 12:59 AM

    how do you run MD01 ?

    try the follows:

    NETCH

    2

    3

    1

    1

    1

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.