Release strategy reversal for the purchase requisition.

Former Member
0 Kudos

Hi all,

I have a scenario were we have three release levels to release the PR through ME54N tcode.

After all the levels are released,If at the first level the PR release is cancelled all other levels are automatically cancelled.

Now my concern is until the 3rd release cancellation is done, 2nd and 1st level should not be allowed to cancel the release of PR. and until 3rd & 2nd release cancelltion is done, 1st level should not be allowed to cancell the release of PR.

Please Let me know if any BADI or any enhancement is available to acheive this back release strategy for PR.

Regards,

Kumar

Edited by: kumar g on Jul 16, 2009 6:21 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

-