Hi all,
We have the R/3 4.6c with 4.2 TB and BW 7.0 with 7.4 TB , during the refresh from prod to quality the BDLS steps takes nealry 24 to 40 hrs . We have break down the tables and kicking off mutliple BDLS jobs like Z * tables in BDLS run and other set of tables in another run so that these jobs will run parallel . During this BDLS conversion only one background process
is running for one BDLS run is there any way to make the load distubution among available background process to so that the conversion will complete sooner.
For example : In R/3 i have trigger one BDLS run for CATSDB table in background this will occupy only one background process, how can we make to use of available all background process to run for CATSDB so that conversion will be completed soon .