Budget from Cost element Planning

How to copy the cost element planning values as budget?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jul 14, 2009 at 02:48 PM

    Hi,

    goto CJ30 select the plan values column, goto menu>edit>select>select all. again goto menu>edit-->copy view.

    or use IMCCP3 - Transfer Plan to Project Budget

    Rgds

    Sudhir Reddy

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 15, 2009 at 06:24 AM

    Hi

    Use IMCCP3 t.code to copy the cost element planning values as budget.

    In processing options if your project budget is alrady has the budget then select the Budget as supplement/return check box. Otherwise system will through the error.

    If you are createing the fresh budget for this project then no need to select the check box.

    Thanks

    S.Murali