cancel
Showing results for 
Search instead for 
Did you mean: 

Planning Horizon

Former Member
0 Kudos

Hi All

In a standard SAP, number of days defined for planning horizon is 100 days. Can anyone explain me what is the logic behind that 100 days?why SAP defined 100 days?

Regards

P.Srinivasan

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

ok

former_member184655
Active Contributor
0 Kudos

Dear Srinivasan,

In my understanding in most of the cases the next 3 months requirement will be considered during MRP run with processing key

as NETPL during MRP run and so the system considers only the requirement that falls within this 100 days for the procurement

proposals and leaves off the remaining period's requirement.

Say for a plant the planning horizon is defined as 100 days in OPPQ and for a material under this plant,there is req for

August,September,october and november for 1000 quantity in each month and the stock is 0 and if you run MRP with

NETPL,you will be able to see the planned order's getting created only for the Req till october (3 planned order's will be

generated)and if you run with NETCH the system considers all the requirement's that fall within and outside the planning horizon.

Regards

Mangalraj.S

former_member219179
Contributor
0 Kudos

Hi According to me Planning Horizon is the number of days we use in MRP Run. This we define in OPPQ as 100 days.The system only plans materials that have undergone a change that is relevant to the planning run within the period which you defined as the planning horizon.

In your case if you want to change the planning horizon to more than 100 days you can cheanged it.

Anway we will wiat for oiur experts reply too.

Cheers,

Kumar.S

Former Member
0 Kudos

HI

in std sap, they maintianed as 100 in planning horizon.

This planning horizon specifies the period for the "Net change planning in the planning horizon".

In this kind of net change planning, only those materials that have undergone a change that is relevant to MRP within the planning horizon ( say 100 days ) are included in the planning run. Such materials receive a net change planning indicator in the planning file.

it means " where a planning file entry is made for the net change planning in the planning horizon. The planning horizon is calculated in workdays "

so for planning file entry is made for the net change planning in the planning horizon for 100days.

You can change as per your customer reqmt.

basically the planning fiel is calculated by :

The length of the planning horizon should include at least the following:

the period in which sales orders are received

the delivery periods

the total lead times of the materials