on 09-01-2018 8:22 AM
Dear All,
I have a two customers, 1. delivery priority is set as high and for second customer delivery priority is set medium.
now in SAP user create the sales orders separately for both customers of a same material.
How delivery priority can be effect while doing the ATP check, is there any customization required, i want system first reserve the quantity for a high delivery priority customers even the SO later after medium priority customers.
Can any one explain how it will work, thanks.
Priority will be given based on the numerical value you set for customer master. For example, as you said, if you set 01 for customer-A and 02 for customer-B, create sale order first for customer-B and then for customer-A, and when execute V_V2, system would consider customer-A only.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear G Lakshmipathi,
While I am running the report, system cant give the output of the report,
Can you please guide me in this regard.
If the Delivery priority is blank, then, that will be considered as the highest priority.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Imran,
please check this thread:
https://archive.sap.com/discussions/thread/1752625
On time, for S/4HANA some assumptions related to ATP were changed because there are a new ATP logic. I´m supposing that you are talking about ECC.
best, FM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.