in ME2o , two deliveries gets created if we select same vendor

Dear All,

We are executing transaction ME2o for one means same vendor with different materials. our aim is that system should create only one delivery (when we click on create delivery). In stead of one delivery system create 2 deliveries.

And green message comes as -Delivery date can not me met,forward scheduling to delivery date

How only one delivery get created.

BR/

Mahesh


Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Sep 05, 2018 at 09:06 AM

    Hello Mahesh,

    Please use ME2ON instead and also implement note "1851720 - ME2ON: Delivery split for deliveries to subcontractor".

    Best regards,

    Diana

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 05, 2018 at 02:22 PM

    HI Diana,

    You mean to say that instead of ME2O ,I need to use ME2oN and it will solve problem of creting 2 deliveries or multiple deliveries.

    Also , me tried to use ME2oN , but there is no checkbox to select.

    getting message as - when we select material and click on create deliveries. Am i doing wrong navigation??

    This function is only possible for purchase orders

    BR/

    Mahesh

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 06, 2018 at 07:11 AM

    HI Diana,

    Me Execuited ME2o and then also noticed 2 deliveries created.

    One observation:

    We we execute program- ZLE_ANALYZE_DELIVERY_SPLIT , to find out why spit delivery happened at that time we noticed that there is differance in HANDLE for both deliveries , so I think thats why this delivery is getting split.

    Do u know about HANDLE ,where we can see it in Delivery or how it gets determined.

    HANDLE Worldwide unique key for LIKP-VBELN

    BR/

    Mahesh