The (internal) unit has not been maintained in the unit table

Dear All,

I have created BOm for a material Cutpcs.I gave the component as Fabric .Unit of measurement for Cutpcs is PC and Fabric is KG.I ran the MRP and created production order for the BOM material.

In confirmation The following error will occur.

"The (internal) unit has not been maintained in the unit table"

Note:These are in AFS

Regards,

D.Deepa

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Jul 11, 2009 at 08:37 AM

    Dear Deepa,

    what happnd to ur MRP thread

    when ever u post a thread, plz make a practice of closing the threads

    in case, if ur not staisfied then u should revert back

    so plz close ur previeous thread

    Thanx for understanding

    Just now a gave a glance of ur MRP thread which has closed by u

    but suprisingly u have not allocated any points to ur repliers

    Plz try to encourage forum members

    Coming to this thread

    just check whether any alterantive unit of measure is maintained fabric

    as ur saying it is KGS, but usually in apperel indutries they buy fabric in ROLLS

    so just check & revert back

    Regards

    kumar

    Edited by: kumar kumar on Jul 11, 2009 10:39 AM

    Edited by: kumar kumar on Jul 11, 2009 11:12 AM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 13, 2009 at 05:47 AM

    Hi Deepa,

    You maintain additional units of measure for the cut pieces like this. 10 Pcs = 1 Kg this is an example. try this and let me know.

    Regards

    Ramana

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 30, 2009 at 06:09 AM

    Hi Deepa,

    I m also encountering the same error msg "The (internal) unit has not been maintained in the unit table". Can u pls send me the solution.

    Rajeev

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 15, 2013 at 01:05 PM

    Hi Deepa,

    I know this que'n has been asked a long time back but am answering it now becos I have this problem currently.

    The solutions provided by other collegues seems to be wrong becos SAP is some how triggering this wrong error mesg. where it should not !

    We had same error but we realized that picking of MMs for lower level production orders and their confirmations were not done entirely. Once this has been done...the error vanished 😊

    So check the BOMs lower level MMs and their respective production orders and do GI of those components and confirm all operations on those production orders.

    Hope this might help any other fellas who are encountering this error mesg.